Hi,

Could you please tell me what is the impact on checking that option to YES?

Thanks.


 
Posted : 09 Apr 2020 20H44
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

If this parameter is set to YES
If you have Activities this way
A1 - recorded
A1.1 - recorded
A1.2 - recorded
When first sub-activity moves to "in progress", parent also moves to is progress
A1 - in progress => changed automatically
A1.1 - in progress => changed manually
A1.2 - recorded
When last sub-activity moves to done status, parent also moves to done status
A1 - done => changed automatically
A1.1 - done => changed manually
A1.2 - rdone => changed manually


 
Posted : 09 Apr 2020 21H14
 BILA
(@lsigroup)
Posts: 304
Contributor
Topic starter
 

Really good option !!
Could you please tell me if it works with activity as mother and link ticket as child for example?
Or with Meeting as mother and linked ticket as child ?
Or with Action as mother and linked ticket as child ?

Thanks


 
Posted : 10 Apr 2020 13H35
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Could you please tell me if it works with activity as mother and link ticket as child for example?

No

Or with Meeting as mother and linked ticket as child ?

No

Or with Action as mother and linked ticket as child ?

No

It only works with "planable" items (items displayed on Gantt chart)


 