Hi all,
i've installed the 7.4.2 version. One of the most promising new feature is the possibility to place, in planning view, activity at a give place. Con someone explain how to do this? I can't find a way to do that.
Thks in advance,
Stefano
In the gantt view, select any item (project, activity or milstone) and "add" new activity with the "create new item" button on top of screen (beside filter).
Just create your activity as usual : it will automatically be placed "after" the selected item (or under if you selected a project)
Thank you very much