 Raja
(@raja-ouji)
Posts: 5
Active Member
Topic starter
 
[#5423]

Hi,
for what I find the cost and the expenses in a window and I find it not in the other ?
thanks


 
Posted : 14 Sep 2018 15H59
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Possibily because admin gave visibility on cost only to project leaders, and your not project leader on one of the project.


 
Posted : 14 Sep 2018 16H14
 Raja
(@raja-ouji)
Posts: 5
Active Member
Topic starter
 

Hello,
why the cost field does not appear with my account but it appears with the account of my colleague ?? both account is with profile: Administrator.


 
Posted : 25 Sep 2018 14H05
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Because admin defined that your profile should not see costs.


 
Posted : 25 Sep 2018 14H19
 Raja
(@raja-ouji)
Posts: 5
Active Member
Topic starter
 

Hello
I want to change the cost of the project, but the field and greyed out, do not give me permission ??
My prifile is: Administrator


 
Posted : 25 Sep 2018 16H23
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

It means the costs (and work) are consolidate from activities and/or sub-projects

See global parameter : consolidation of validated work


 
Posted : 25 Sep 2018 16H54