[#5423]

Hi,
for what I find the cost and the expenses in a window and I find it not in the other ?
thanks


 
Posté : 14/09/2018 3:59 pm
(@babynus)
Posts: 14952
Membre Admin
 

Possibily because admin gave visibility on cost only to project leaders, and your not project leader on one of the project.


 
Posté : 14/09/2018 4:14 pm
 Raja
(@raja-ouji)
Posts: 5
Active Member
Début du sujet
 

Hello,
why the cost field does not appear with my account but it appears with the account of my colleague ?? both account is with profile: Administrator.


 
Posté : 25/09/2018 2:05 pm
(@babynus)
Posts: 14952
Membre Admin
 

Because admin defined that your profile should not see costs.


 
Posté : 25/09/2018 2:19 pm
 Raja
(@raja-ouji)
Posts: 5
Active Member
Début du sujet
 

Hello
I want to change the cost of the project, but the field and greyed out, do not give me permission ??
My prifile is: Administrator


 
Posté : 25/09/2018 4:23 pm
(@babynus)
Posts: 14952
Membre Admin
 

It means the costs (and work) are consolidate from activities and/or sub-projects

See global parameter : consolidation of validated work


 
Posté : 25/09/2018 4:54 pm