Hi,
I would like an activity with a fixed date.
Is it possible to block one date on planning mode.
Thanks you
Best regard
Posted : 27 Oct 2012 17H02
Two ways :
1) use one of the planning modes "regular between dates"
2) Put a "fixed" Milestone to the date and set dependency to the task
Posted : 27 Oct 2012 17H21