Hi,
Is it possible to set the fixed start date for the activity?
In this case it should have priority against other tasks where resources are the same.
Regards,
Evgueni
Is it possible to set the fixed start date for the activity?
Two possibilities :
- either set a fixed dates planning mode
- or define a fixed milestone and add a dependency from milestone to task
In this case it should have priority against other tasks where resources are the same.
Not by default, you have to set the priority.
Thank you very much!
Regards,
Evgueni