GANTT problem
 
Notifications
Clear all

GANTT problem

4 Posts
3 Users
0 Reactions
3,892 Views
(@nibulus)
Posts: 14
Active Member
Topic starter
 
[#2410]

Hello everyone,

I have a question for you guys. I created two tasks, the second one can't start before the end of the first one. In my GANTT graph they are link. For this everything it's ok. But if i change the date of the first task beginning, something like two weeks after the initial start of the second one. Nothing change on my GANTT, why the second task don't move to be after the first one ?

Hope you could help me.

Thx in advance.


 
Posted : 03 Jul 2015 12H46
(@richard-pare)
Posts: 165
Active Member
 

Do you have real work imputation in second task ?

If you have real work, real dates are set. So, planned dates don't change.


 
Posted : 03 Jul 2015 17H46
(@nibulus)
Posts: 14
Active Member
Topic starter
 

Not for the moment.

They are just planned without any imputation.


 
Posted : 03 Jul 2015 18H01
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

1) be sure to run planning calculation

2) ProjeQtOr is work driven : so if you don't define assigned work, you have to specify some coherent planning mode, such as "fix duration" to have correct planning calculation.


 
Posted : 03 Jul 2015 18H50