Gantt representation for connection between activities

2 Posts
2 Users
0 Reactions
2,820 Views
Florent MOYER
(@fmoyer)
Posts: 26
Active Member
Topic starter
 
[#5491]

Hello,

When an milestone is connecting to an activity with end-begin connector, the arrow start at the beginning of the milestone.
Why ?

Thanks
Florent


 
Posted : 15 Oct 2018 17H03
Gautier
(@gautier)
Posts: 207
Active Member Admin Registered
 

Hello,

The arrow start at the beginning of the milestone because there is not duration in milestone.
Connect milestones to an activity with end-begin or begin-begin is the same things.
Furthermore graphically is more readable to start at the beginning of the milestone when you have lot of dependencies.


 
Posted : 15 Oct 2018 19H08