Gantt representation for connection between activities

2 Posts
2 Utilisateurs
0 Reactions
2,804 Vu
Florent MOYER
(@fmoyer)
Posts: 26
Trusted Member
Début du sujet
 
[#5491]

Hello,

When an milestone is connecting to an activity with end-begin connector, the arrow start at the beginning of the milestone.
Why ?

Thanks
Florent


 
Posté : 15/10/2018 5:03 pm
Gautier
(@gautier)
Posts: 207
Membre Admin Registered
 

Hello,

The arrow start at the beginning of the milestone because there is not duration in milestone.
Connect milestones to an activity with end-begin or begin-begin is the same things.
Furthermore graphically is more readable to start at the beginning of the milestone when you have lot of dependencies.


 
Posté : 15/10/2018 7:08 pm