Hi,
I´m new to projeqtor and new to the forum.I started with this software to manage a private project.
I have problems by using the Tasks in projects.
These are those 2 problems (I added screenshots for each problem):
- When then "editet" checkmark is set I cant remove it anymore. Is it possible? If yes, how? (screenshot 1)
- When a planned start and end Date is set I cant remove it anymore. I even cant change it. Any tips? (screenshot 2)
- I cant manual edit the progess in procent of the Tasks. Its always on 0 %. Only if I set it to "done" it goes to 100 %. How can I edit it manual? (screenshot 3)
I hope someone can help me, cause I want to continue use this software.
Thanks.
Andre
Hi,
By defaukt, Projeqtor provides a work driven capacity planning.
This means :
- planned dates are calculated, not defined by hand.
- progress is defined from Timesheet entries : rela work follow-up will calculate progress.
If you want to define a "manual" planning, use only "fixed duration" tasks, and in global parameters select option "manual progress for fixed duration tasks"