Is it possible to hide command "enter real as planned" of Rea Work allocation view for some user profiles ?
Hello,
This is not possible for the moment, It is a good idea.
I recorded as Ticket #3334.
This evolution will have low priority in our roadmap.
Hi,
We are using V6.5.5 . What is the main function of "enter real as planned" button? When we tried to use, nothing was changed on table .(First we assigned work in activity, then we calculated the planing) Also when we use this button the allocation takes place according to what?
Thanks.
This feature does nothing unless you check "show planned work"
(it will show planned work in small blue fiugures)
We added a message on V7.0 to alert on this.