How can I calculate Schedule Variance and Effort Variance in the tool

3 Posts
3 Users
0 Reactions
1,720 Views
(@shobhana-mahantigmail-com)
Posts: 4
Active Member
Topic starter
 
[#6710]

How can I calculate Schedule Variance and Effort Variance in the tool


 
Posted : 14 May 2020 16H14
(@alain-fourastie)
Posts: 366
Member Moderator
 

hi
A pool is an aggregation of unit resources to be planned as a single resource. When you allocate resources to the pool you define its capacity on one or several periods. Then you will plan the pool as a usual resource with its constraints given considering itself the resources's constraints. Please read the friendly usuer manual about pool.


 
Posted : 15 May 2020 11H24
(@babynus)
Posts: 14952
Member Admin
 

ProjeQtOr does not manage earned value yet.
But you can get project variance through report "S-curve chart".
You'll need to define a baseline (the reference for the variance) to have it work.


 
Posted : 18 May 2020 20H14