How FTE variation works?

13 Posts
3 Users
0 Reactions
5,822 Views
(@rakoun)
Posts: 29
Active Member
Topic starter
 
[#6610]

Bonjour,

I discover a very nice functionnality in Projeqtor, the ability to set FTE for a period.
So I set my ressource's default FTE to 1 and I set a COVID-19 FTE to 0.5 in "FTE variation" from 01/04/2020 to 31/05/2020.
But when I return to my gannt view and ask projeqtor to calculate my project, for a task with a charge of 8 hours it does not change its real spent time to 2 days but lets 1 day.

What is wrong in my configuration?

PS: 8 hours is my default number of working hour in a day

Regards,


 
Posted : 06 Apr 2020 6H21
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

There's nothing wrong with your configuration, it's about undestanding what variation of capacity is.
It does not change duration of a day, so that a full work day is now half a day.
Moreover it won't impact real work entered.
It is just a way to plan the resource with a different capacity than usual one.
For exemple if you need the resource to work for extra time every day to cover some extra work during a period.
It can also be (for covid period) that the resource will be planned only half days during the period.
But it's only for planning, it won't have any effect on real work entered. It will just point out in timesheet that only 0,5 day is expected (sum for day is green when sum entered is 0,5), but resource is always able to enter more (or less) to reflect what he really worked.


 
Posted : 06 Apr 2020 12H38
(@rakoun)
Posts: 29
Active Member
Topic starter
 

There's nothing wrong with your configuration, it's about undestanding what variation of capacity is.
It does not change duration of a day, so that a full work day is now half a day.
Moreover it won't impact real work entered.
It is just a way to plan the resource with a different capacity than usual one.
For exemple if you need the resource to work for extra time every day to cover some extra work during a period.
It can also be (for covid period) that the resource will be planned only half days during the period.
But it's only for planning, it won't have any effect on real work entered. It will just point out in timesheet that only 0,5 day is expected (sum for day is green when sum entered is 0,5), but resource is always able to enter more (or less) to reflect what he really worked.

Thanks for the answer. So do I need to set my tasks charge to 50%?

Regards,


 
Posted : 06 Apr 2020 13H42
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Thanks for the answer. So do I need to set my tasks charge to 50%?

If you mean "assignment rate at 50%", NO.
Resource capacity to 0,5 will be enough to limit planning.


 
Posted : 06 Apr 2020 17H35
(@rakoun)
Posts: 29
Active Member
Topic starter
 

Hum...

Perhaps I did not understand.

Below my configuration with standard FTE of 1 and no variation:

And below a task in my planning with this configuration (task duration is 8h):

Now I change my FTE configuration inserting a period of variation with a FTE of 0.5 and keep a standard FTE of 1. (the example task is in the period and begin 15 june)

this is the result on my planning?

I expected that Projeqtor will put the task on two days and not only one day.

What is wrong?

Regards,


 
Posted : 13 May 2020 18H07
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

Hello

Please , post on the forum directly to make it easier for our community


 
Posted : 14 May 2020 10H47
(@rakoun)
Posts: 29
Active Member
Topic starter
 

Hello

Please , post on the forum directly to make it easier for our community

?, what do you mean. It is not the forum here?

Regards,


 
Posted : 14 May 2020 13H33
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Import images in the forum, and add image in the message, instead of posting links to your dropbox


 
Posted : 14 May 2020 13H59
(@rakoun)
Posts: 29
Active Member
Topic starter
 

Ok, my post as you want it is.

Hum...

Perhaps I did not understand.

Below my configuration with standard FTE of 1 and no variation:

And below a task in my planning with this configuration (task duration is 8h):

Now I change my FTE configuration inserting a period of variation with a FTE of 0.5 and keep a standard FTE of 1. (the example task is in the period and begin 15 june)

this is the result on my planning?

I expected that Projeqtor will put the task on two days and not only one day.

What is wrong?

Regards,


 
Posted : 14 May 2020 17H11
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

Hi,

it should be, but not necessarily with 0,5 each day ( it is a maximum allowed to be planifed on one or more activities per day)
first, have you recalculated the planning ? i think so.
Secondly, is this resource planned among others projects ?

You can make a right click over the bar in order to watch how the work is planned


 
Posted : 15 May 2020 10H57
(@rakoun)
Posts: 29
Active Member
Topic starter
 

Hello,

It is weird.
Yesterday after all my changes in ETP configuration I recalculated the planning.
Today I recalculated the planning again and I got the following:

So I returned in ETP configuration then removed ETP variation configuration.
I recalculted the planning but unfortunetaly it does not change??

Are there a cron that is launched during night and that is needed by ETP configuration to be OK?

Regards,


 
Posted : 15 May 2020 19H36
(@rakoun)
Posts: 29
Active Member
Topic starter
 

Hello,

It is weird.
Yesterday after all my changes in ETP configuration I recalculated the planning.
Today I recalculated the planning again and I got the following:

So I returned in ETP configuration then removed ETP variation configuration.
I recalculted the planning but unfortunetaly it does not change??

Are there a cron that is launched during night and that is needed by ETP configuration to be OK?

Regards,

Hello,

Any idea, I thinks we are on the verge to close this issue.

Regards,


 
Posted : 18 May 2020 17H21
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 
Are there a cron that is launched during night and that is needed by ETP configuration to be OK?

No, changes are taken into account imlmediatly at planning calculation.
Be sure your project has been calculated (you'll notice in planning view that icon has a little orange spot where project needs recalculating)


 
Posted : 18 May 2020 20H16