Hi,
I have a project but some tasks were finished in the past (ie: today is 21 Oct and the two first tasks were finished at 14 Oct and 16 Oct), how can I simulate this case on ProjeQtOr to avoid to have a lot of tasks with "done status" with the date of today. Is it possible?
Thanks for your help.
Martin
If planning mode is "as soon as possible", ProjeQtOr expects some real work to be entered.
On status "done", real end date will be automatically defined (as last real work input)
Thanks for your quick reply