In connection with my other questions, Can you explain me how to defini the real work for a project, an activity, a milestone and an action.
Thank you.
Yours.
Gabriele Cassano.
Here is how to enter real work :
On Project : you cannot. Project only sums real work entered on activity
On Activity : through real work allocation screen (resources must be assigned to the activity to enter real work)
On Milestone : you cannot. Miltones don't have work nor duration. (have a look at the definition of a milestone)
OIn Action : you cannot. ProjeQtOr don't follow work on Actions. Think of Actions like "TO DO" list