Good morning (again),

In connection with my other questions, Can you explain me how to defini the real work for a project, an activity, a milestone and an action.

Thank you.

Yours.

Gabriele Cassano.


 
Posted : 29 Mar 2018 11H59
Gautier
(@gautier)
Posts: 207
Member Admin Registered
 

Hello,

We created an user documentation, press F1 to use it.
As new user, you should read this. Many things are explained like how to use Real work allocation screen.


 
Posted : 29 Mar 2018 12H21
(@babynus)
Posts: 14952
Member Admin
 

Here is how to enter real work :

On Project : you cannot. Project only sums real work entered on activity
On Activity : through real work allocation screen (resources must be assigned to the activity to enter real work)
On Milestone : you cannot. Miltones don't have work nor duration. (have a look at the definition of a milestone)
OIn Action : you cannot. ProjeQtOr don't follow work on Actions. Think of Actions like "TO DO" list


 
Posted : 29 Mar 2018 21H39