Hi Liujian,
planned values will be entered automatically once you run "planning" (Follow up - planning - press button calculate
- select your project - press OK.
Klaus
Project'Or RIA planning is work driven.
Only exception : activities with planning mode = "Fixed duration" don't need work.
You must :
- assign resource to the activities and defined assigned work
- go to "Planning" and run planning.
=> planned dates will be calculated.
Have a look at the online manual, it may help.
RTFM 😉
Regards.
Nice,Thank you!