Hello,
Discovering this great and very rich application.
Although I have been searching the online help and forum, I didn't found how to manage ressource availability in the planning of my different projetcs: I mean how can a planning be automatically reajusted when a ressource is taking vacancies ?
(sorry for my poor English written)
Many thanks.
FR
Hi,
Just create a project for the "off days" of resource.
The project type "Administrative" is done for that.
For instance you can create 1 project "Off'" (project type administrative) with activities such as Hollidays, Sickness, ....
For administrative projects, you don't have to affect resource to project nor assign resource to activitie : resources can directly input real work on these activities.
Then the way to book resource time is to enter real work in the futrure.