I have the situation now where a Ticket is marked as in progress by one "responsible person" but I now need to transfer ticket to a second person due availability. I cannot seem to work out how to achieve this?


 
Posté : 12 Jan PM 14:011
(@babynus)
Posts: 14952
Membre Admin
 

Just change responsible ...


 
Posté : 14 Jan PM 13:011
(@steve-n_22)
Posts: 12
Active Member
Début du sujet
 

Thank you for the reply.
I cannot select from the Responsible Drop-down box (see fig).

If I go for Magnifying glass I get a summary of current Responsible.
If I go For Arrow head I see the people list but cannot select them.

My work around (or possibly the correct way) is to change the current Responsible to just "Blank" via the Drop-down, hit Save Icon.
Now I can go back and change Responsible using the Magnifying glass Icon.


 
Posté : 14 Jan PM 19:011
(@babynus)
Posts: 14952
Membre Admin
 

If new responsible is not is the combo list, it is because he is not allocated to the project.
So selecting a resource not allocated is possible, but possible user won't have access rights to ticket...

NB : when responsible is selected, magnifier show detzil of selected item, but then (on detail display) new magnifyer gives access ti full lsit.


 
Posté : 14 Jan PM 20:011
(@steve-n_22)
Posts: 12
Active Member
Début du sujet
 

I have tried out your suggestions and all is good now.
Item Closed.
Many Thanks


 
Posté : 14 Jan PM 21:011