Hi,
we use projeqtor 9.5.5 for project management and some SaaS services : for Human resources management and unavailability period (leaves and other) and for collaborative work and meeting ( office 365)
I search and see some post about external calendars with projeqtor but seam to only talk about export projeqtor calendar to external.
My need is to import external calendar to integrate ressources unavailability for projeqtor planning without manually re-enter diaries off each ressources.
So there is a way to connect or import external calendar into projeqtor for each ressources to know availability for planning ?
regards,
vlepetit
ok i see this post : https://www.projeqtor.org/fr/kunena/3-propose-evolutions/12601-integrating-yasumi-library#34120
I understand that to integrate external calendar is complex but it's can very help to automate integration of unavailabilty period between differente ressource availability sources.
Regards,
vlepetit
To import "non working days" for resource, just import some "Work" on activity of Administrative project.
Thanks,
i have seen i can import manually activities from tools menu. i'll try to export this périod from our SaaS tools in csv or excel format and import it for each ressource in administrative project.
It's may be a good idear to permit automatic import of this type of calendar by user/ressource from external URL.
Can i propose this evolution in forum ?
Regards,
vlepetit
Request recorded as Ticket #7192
To be honest, as it seems to be a very specific need, I'm not sure it will be done in a near future (unless members of the users QLUB vote for it or it is sponsored by someone)