Hi,

The team projet have a reccurent activity of Support dispatched on all ressources of the team. Each one is turn, every member is on an this activity Support (duration : 1 week).This activity is planified on another tool and i need to import it on Projeqtor directly as an imputation, not as a charge (an administrative project have been created, and an activity "Support").

- Is there a way to import imputations on Projeqtor ? I don't find it on Outils > Importer des données.
The model i want to use is the export file found on Suivi > Imputation.

- When a ressource have an actiivty on a fixed day (impossible to be another day than this one), I see on the user guide than a planning mode exists for that "fixed date" but it is not on the dropdown menu.

How do i find it ?

Regards

Yann


 
Posté : 13 Juin AM 10:066
(@babynus)
Posts: 14952
Membre Admin
 

Imputation, is input of "work".
So you just need to import "work"


 
Posté : 13 Juin PM 12:066
(@yannobi)
Posts: 69
Active Member
Début du sujet
 

Once again, thanks a lot fir the answer.

And how for the planning mode "fixed date". Why do i not find it in the menu ?


 
Posté : 13 Juin PM 14:066
(@babynus)
Posts: 14952
Membre Admin
 

And how for the planning mode "fixed date". Why do i not find it in the menu ?

What do you mean ?


 
Posté : 13 Juin PM 16:066
(@yannobi)
Posts: 69
Active Member
Début du sujet
 

In an activity, i can't find the planning mode named "fixed date".


 
Posté : 13 Juin PM 17:066
(@babynus)
Posts: 14952
Membre Admin
 

Because there is none with this name.
Have a look at "regular between dates". I think it is what you are looking for.


 
Posté : 13 Juin PM 17:066
jmmbb
(@jmmbb)
Posts: 561
Contributor
 

look at "Régulier entre deux dates".