Indicator questions
 
Notifications
Clear all

Indicator questions

3 Posts
2 Users
0 Reactions
3,451 Views
(@tjaeckle)
Posts: 15
Active Member
Topic starter
 
[#2868]

Hello!

1. Is there a way to define an indicator/alert/warning/email for a fixed milestone if the predecessor elements has a later validated/planned/reassessed end date? In small projects it is no problem to check this by hand, but in bigger projects this can become a problem! And it would be important to detect such things, as this is an indication for a delayed project.

2. I started with an indicator for an activity with reassessed work compared to validated work > 100%. This indicator was never activated. After some search I found, that the validated work was 0d the reassessed 6d but the indication failed. If I set validated work to 1 the indicator works as expected.
Why is 6d not more than 100% bigger than 0d? Is this a bug or is there a good reason for it?

3. In Toady screen tasks with active indicators have a red background. It would be very useful, if a similar indication could be seen e.g. in Activites/Milestones screen and in gantt planning on the left in the task column. Is this somehow available or would this be a feature request? This would speed up planning if I don't have to change always to Today screen.

Best regards
Thomas


 
Posted : 08 Jan 2016 12H32
(@babynus)
Posts: 14952
Member Admin
 

1. ]No. Not on fixed milestone.
Only way to do it : set milestone as floating, so that it will move corresponding to end of predecessor, and define an alert on the milestone

2. Validated = 0 means value is not defined, so alerts are not triggered : it would genereate too many alerts on project definition 😉

3. Indicator appears on item, but not in lists. It is a good idea to show it in lists, including planning. Request recorded as Ticket #. (Will have to care of performance)


 
Posted : 10 Jan 2016 20H45
(@tjaeckle)
Posts: 15
Active Member
Topic starter
 

Hello!

Sorry for the late answer, I just came back to this problem now.
Concerning 1.:
I have a Project with 10 weeks duration and a floating milestone at the end. I have already set an alert to respect of planned end date with let say 5 days. After 2 weeks of the project there rises an additional task with 2 more weeks. So planned date is shifted and also the 5 days alert is shifted. So the alert will become active one week after the initial end date! That is too late.

What I would like to have is an alert, that the milestone has been shifted. Something like "planned date compared to validated date" or something like this.

Alternative:
In planning mode the delay of the milestone is recognized and displayed. Would it be possible to display this delay also in the milestones form in one row?

Is there any other solution to detect such cases as early as possible?

Best regards
Thomas


 
Posted : 21 Mar 2016 20H02