Hello

In our environment we need to produce the following KPI reports :

- days and costs margin (reassessed vs validated), by project (no need for activity details), something like this :

Project Work validated Work real Work left Work reassessed Work progress % Work margin %(reassessed/validated) Cost validated Cost real Cost left Cost reassessed Cost margin %(reassessed/validated)

Our objectives are :
- work margin < 100%
- cost margin < 75%

- Resource occupancy rate by project type (for one month and one team)

Resource Fixed prices % Time & Material % Internal % Administrative %
Resource1
Total team

Then we would need something a bit more complicated because our objectives are :
- (Fixed price + Time&Material) / (Total - Administrative) < 75%
Simplest way to phrase it : we want to check and monitor the intercontract rate.
So we could simplify to this (but intercontract rate is probably more ambiguous to calculate)

Resource Busy % Intercontract %
Resource1
Total team

Is there a way to do this ?


 
Posté : 5 Jan PM 20:011
(@babynus)
Posts: 14952
Membre Admin
 

There is no direct way to have all of this on one page, but all required data exist.
You have to build a specific report to have this overview in one glance.
We can do it for you if you wish : Contact us through the contact form.

NB the margin definition in ProjeQtOr is different from what you expect.
Margin = Validated - Reassessed
Margin in % = (Validated - Reassessed) / Validated
So I guess that what you expect is :
- work margin > 0%
- cost margin > 25%


 
Posté : 5 Jan PM 20:011
(@guilhem)
Posts: 30
Active Member
Début du sujet
 

OK I will investigate custom reports and let you know

Thanks for the margin, it is actually much more logical like this


 