Hello everyone,

I want to manage leaves using the 'regulated leaves' module.
Is it normal for the project created automatically by the module (named PROJECT - LEAVE PERIOD) to be invisible in the 'projects' section?
Leaves are not represented in the 'planning > critical resources' section, 'workload plan' tab. Absences could affect either the forecasted load (colored bars) or the resource's capacity, don't you think?

By the way, a very rich tool, well done!


 
Posté : 22 Juil PM 19:077
(@marylene)
Posts: 592
Membre Admin
 

Is it normal that the project automatically created by the module (named PROJECT - HOLIDAY PERIOD) is invisible in the 'projects' section?

yes, this is the expected behavior.

As for critical resources, this is a sponsored development. Do not hesitate to ask for a quote to improve this feature


 
Posté : 23 Juil AM 10:077