Hello,
I'm not able to link activities (predecessor/sucessor) between different sub-projects.
My purpose is to tell projeqtor : don't plan this ressource to this task of this project until this other task of this other project is finished.
When selecting predecessor list, I only find activities of the current sub-project.
Any solution ?
2 solutions :
1) when adding dependency, use the search button (little magnifyer) beside activities list.
You will then be proposed a list of all activities you have access to, whatever the project. 🙂
2) On planning view, create link with drag & drop :woohoo:
Just wonderfull !