Hello,
I'm not able to link activities (predecessor/sucessor) between different sub-projects.
My purpose is to tell projeqtor : don't plan this ressource to this task of this project until this other task of this other project is finished.

When selecting predecessor list, I only find activities of the current sub-project.

Any solution ?


 
Posted : 10 Jul 2014 20H47
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

2 solutions :

1) when adding dependency, use the search button (little magnifyer) beside activities list.
You will then be proposed a list of all activities you have access to, whatever the project. 🙂

2) On planning view, create link with drag & drop :woohoo:


 
Posted : 10 Jul 2014 20H56
(@badgamme)
Posts: 32
Active Member
Topic starter
 

Just wonderfull !


 
Posted : 10 Jul 2014 21H04