Link delay in calendar days, not in working days

4 Posts
2 Utilisateurs
0 Reactions
2,771 Vu
Bena
 Bena
(@bena)
Posts: 65
Active Member
Début du sujet
 
[#5078]

Hello,

Is it possible to add a delay on a link between activities in calendar days, not in working days ?

Thanks for your wonderfull app 🙂

Regards.


--
Bena

 
Posté : 12 Avr PM 19:044
(@babynus)
Posts: 14952
Membre Admin
 

No, delay is alway in "open days"


 
Posté : 12 Avr PM 20:044
Bena
 Bena
(@bena)
Posts: 65
Active Member
Début du sujet
 

In fact, I need, for legal constraint, to wait X days (not open days) after an activity.
Currently, I choose the strating date of the following activities but of course, I have to change it manually when the planification of the previous task change.
Do you have an idea about doing that in a better way so that the next activity move automatically ?


--
Bena

 
Posté : 14 Avr AM 10:044
(@babynus)
Posts: 14952
Membre Admin
 

Do you have an idea about doing that in a better way so that the next activity move automatically ?

As of today, there is no way to do this.
Delays are always in open days.
What you want would need an evolution. Two possibilities :
- New planning mode "fixed calendar duration" (similar to "fixed duration" but in calendar days, not working days)
- Possibility to define that delays on dependencies are in "calendar day" instead of "working days" (new checkbox in the definition of dependency)
Possbily both evolutions could be done.

I recorded both as Tickets #3318 and #3319
Sure this evolution will have very low priority in our roadmap.

If you need these, you may consider sponsoring the devs to have them in the next release of ProjeQtOr.
Please contact us through the contact for to get a quote for the devs.


 