Hi Everyone,
I would like to know if it is possible to manage ProjeQtOr upgrade.
On the one hand upgrade is good to receive new functionnalities or fixes, but on the other hand it make ProjeQtOr not functionnal (an error like "Upgrade in progress. Only admin user can connect" appears).
So my questions are:
- Is it possible to specify the period to start the upgrade (for example at midnight) to not perturb users.
- Or completly deactivate ProjeQtOr upgrade.
Thanks in advance for any responses.
You manage upgrades whenever you want !
Message
"Upgrade in progress. Only admin user can connect"
is not an error, just a message to way until upgrade is finished.
NB : the tool waits for the connection of an administrator to finish the upgrade...
Hello Babynus,
Thanks a lot for your response.
Nonetheless it is a good thing to have a functionnality to manage upgrade, instead of waitting an administrator to log in to finish the process.
If the functionnality is already present, could you please indicate how to access it?
Regards,
Tsara
It should be the administrator that runs the upgrade... no ?
So last task to finish upgrade is just to connect (with admin account).