Milestone depending on another milestome

3 Posts
2 Users
0 Reactions
4,183 Views
Jörg Friedrich
(@friedel)
Posts: 5
Active Member
Topic starter
 
[#1974]

Hello,

first of all, thank you your a great software.

I try to setup a templete of 5 phases project (used in automotive business) and there are some milestones which depends on other (e.g. the last milestone should be 90 days after some other milestone). Is there a possiblity tho implement such a date? And how con I do this.

Thank you for your help.
Friedel


There is nothing good, except you do it. (Erich Kästner)

 
Posted : 30 Aug 2014 17H33
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Yes, you can do this.
And you can do this in two different ways :

1) When creating the dependency between milestones, you can add a delay between them.
Just set the delay to 90 days and you'll get exactly what you want

2) Another way to do this is to add a "Fixed duration" task between the milestones.
Fixed duration to 90 days, with do what you expect, with first milestone predecessor of task and second successor of it.
It is a bit longer, but will allow to represent why there is a gap between milestones.

Just pay attention that ProjeQtOr always consider "Open" days.


 
Posted : 30 Aug 2014 18H04
Jörg Friedrich
(@friedel)
Posts: 5
Active Member
Topic starter
 

Hello badynus,
thank you for your fast response. It works.

Thank you


There is nothing good, except you do it. (Erich Kästner)

 
Posted : 30 Aug 2014 18H45