Hi,

I don't know if it's an issue or if I don't understand well (in that case, thank you for explaining me how I can achieve it), but when a milestone is the last element of the project, and is done (so it looks like capture1.png), real is correctly inserted.

However, when we go on the project, no real end date is inputted, see capture2.png.

(I don't know if that matters but these projects only contained milestones, as there are only deliveries from our suppliers).

Thanks in advance,


 
Posté : 26 Avr AM 11:044
(@babynus)
Posts: 14952
Membre Admin
 

However, when we go on the project, no real end date is inputted, see capture2.png.

End date of project is not defined until Project status is set to done...


 
Posté : 26 Avr PM 16:044