Hi babynus,

one question, is it possible when there is no assignation on task that pojeqtor had the same behavior than MS Project.

this mean to day projeqtor behavior is : when i have a task with duration but no date nor assignation wich is linked with another task the first one is not planned. no bar in gantt chart. In project the task duration is shown and the constraint ( the link to the precious or next task) is taken into account to fix the start and end date.

i don"t know if im clear ?!!!!

thank's for all.


 
Posté : 10/06/2015 10:47 am
(@babynus)
Posts: 14952
Membre Admin
 

There are some kind of improvements this way in V5.0, except that duration is taken into account only if planning mode is "fixed duration".
Your proposale is interesting. I'll have a look to see if this can be completed before V5.0 deployment.


 