MS Project Like --> configuration

2 Posts
2 Utilisateurs
0 Reactions
1,285 Vu
(@iflorian)
Posts: 63
Estimable Member
Début du sujet
 
[#8849]

Hi there,
Today, I made a presentation of ProjeQtOr in a Direction of my Collectivity and it was rejected under the pretext that one could not reproduce the ergonomics of MS Project:
-  to be able to modify the start and end dates directly on the planning line,
- to be able to stretch the tasks directly from the planning. 
- to be able to move a task into a subtask graphically from the planning. 

Is there any possibility of reproducing this behaviours ? 
Obviously, they have a very basic use of the tool: only planning management... 
The complaint is that changing the screen or splitting the screen into several parts is a waste of time for them. 

It's not easy to get the tool adopted by businesses other than the IT department. 

I look forward to hearing from you,
Best regards,
Florian 
 


“Be a yardstick of quality. Some people aren't used to an environment where excellence is expected.” ~ Steve Jobs
"...and while some may see them as the crazy ones, we see genius, because the ones who are crazy enough to think that they can change the world, are the ones who do." ~ Think Different

 
Posté : 04/04/2023 7:19 pm
(@babynus)
Posts: 14952
Membre Admin
 

-  to be able to modify the start and end dates directly on the planning line,

It is possible for "ragular between dates" tasks

- to be able to stretch the tasks directly from the planning. 

It is possible for "fix duration" tasks

- to be able to move a task into a subtask graphically from the planning. 

It is possible with D&D and Indent buttons.

Maybe Projeqtor is not "as easy" as MS-Project because it is not a drawing tool.
It is a tool that builds a capacity planning.


 
Posté : 06/04/2023 7:47 pm