Hi,
In Multiple Update Mode of Activity Section, can it be possible that assignment of a resource to muttiple tasks?
Thanks in advance.
Posté : 25 Juil PM 17:077
No, this is not possible through Multiple Update, selection and design is not adapted to this purpose.
This is subject of Ticket #1825 "Add multiple assignement management"