Hello,
Is it possible to sort the project activities in the schedule display ?
Thanks for your help.
Posté : 15 Nov AM 11:1111
Yes :
Inside a given level, just drag and drop an activity
Posté : 15 Nov AM 11:1111
If your print screen if from Gantt Planning view (and not resource planning view), you should be able to move the activity as you describe.
When you move the activity, is the header of the move item "green" or red when you drop it ?
Posté : 15 Nov PM 12:1111
Début du sujet
No, the header is red and say that is not possible but i dont know why ?