"parent activity" field

4 Posts
2 Utilisateurs
0 Reactions
2,601 Vu
Martin
(@el-wallos)
Posts: 220
Active Member
Début du sujet
 
[#2894]

Hi

What the goal of the "parent activity" (activité parente in french) field for a task? because dependence is generated by succesor/predecessor filed.

Thanks.


 
Posté : 12 Jan PM 16:011
(@babynus)
Posts: 14952
Membre Admin
 

Parent will determine the level in the WBS : task will become a sub-task of the parent.


 
Posté : 12 Jan PM 16:011
Martin
(@el-wallos)
Posts: 220
Active Member
Début du sujet
 

So, what is the difference between sub project and sub task?


 
Posté : 12 Jan PM 18:011
(@babynus)
Posts: 14952
Membre Admin
 

In most concerns there is no.
You can split in project / sub-projects / tasks / sub-tasks as you wish.
But some differences exist, like :
- access rights are defined at project (and possibly or sub-project) level
- access rights calculation may lead to performance issue is you cometo define too many projects


 
Posté : 12 Jan PM 19:011