Part time salary
 
Notifications
Clear all

Part time salary

6 Posts
3 Users
0 Reactions
1,962 Views
 BILA
(@lsigroup)
Posts: 304
Contributor
Topic starter
 
[#6125]

Hi,

how is it possible to say to the system that a user is not working on wednesday afternoon for example?
In consequence, we are not able to give himwork on that period.

Thanks


 
Posted : 12 Jul 2019 16H35
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

HI,

To take into account the half days, you must go through the screen " absences" or " timesheet" and fill half a day as day off.

Regards.


 
Posted : 12 Jul 2019 16H51
 BILA
(@lsigroup)
Posts: 304
Contributor
Topic starter
 

Hi Alain,
ok but it is a recurrent absence (all wednesday afternoon),
It is not occasionally


 
Posted : 12 Jul 2019 16H53
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

HI Damian,

I know ! we work on full day that why you have just to spent one and half minute to fill all the wednesdays of the year ...;-) that s the only way. It s done quicker through the screen "absence"

Best regards.


 
Posted : 12 Jul 2019 17H07
 BILA
(@lsigroup)
Posts: 304
Contributor
Topic starter
 

Hi,
Ok but how to proceed as i do not want to have an impact on my employee holliday counter? The objective is just to avoid having tasks planned on that particular half-day which is weekly


 
Posted : 04 Apr 2020 3H00
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Just add a specific administrative task (off duty or partial time).


 
Posted : 05 Apr 2020 16H07