Hi,
how is it possible to say to the system that a user is not working on wednesday afternoon for example?
In consequence, we are not able to give himwork on that period.
Thanks
HI,
To take into account the half days, you must go through the screen " absences" or " timesheet" and fill half a day as day off.
Regards.
Hi Alain,
ok but it is a recurrent absence (all wednesday afternoon),
It is not occasionally
HI Damian,
I know ! we work on full day that why you have just to spent one and half minute to fill all the wednesdays of the year ...;-) that s the only way. It s done quicker through the screen "absence"
Best regards.
Hi,
Ok but how to proceed as i do not want to have an impact on my employee holliday counter? The objective is just to avoid having tasks planned on that particular half-day which is weekly
Just add a specific administrative task (off duty or partial time).