Hi,

I have defined a periodic meeting (10 dates fixed every week at monday).
But in my planning these meetings all appear assigned on the creation date.

I don't understand how to assigned meetings on corrects days.

Thx for you help


 
Posté : 25/01/2016 7:32 pm
(@babynus)
Posts: 14952
Membre Admin
 

You did not assign resources to Meetings.


 
Posté : 27/01/2016 12:00 am
Martin
(@el-wallos)
Posts: 220
Active Member
 

Update the assign work (travail assigné) for the user CP1), with the pen on "participants" tab and rebuild the planning if it is necessary.


 