Hi babynus, hi Everybody,
I'm facing a strange behaviour of Projeqtor, It doesn"t generate meetings since 2024/09/30. This means in my project which end 2024/12/31, the weekly stops at end of september, and the monthly too.
Not possible to have auto generated meeting since this date !?
Do i forgot something ? is there any parameter which impact the meeting génération ?
Thank's for your help ..
Hello
Periodics meetings are not dynamic.
If the project extends in time after creating the meetings then the dates of the recurring meeting will not update themselves.
You will have to go and update the dates manually to create the new meetings.
Hi arkhanje,
thank's for your reply,
But i already done that,, i mean, i updated the finished project date, i updated the periodic meeting object with the new date (using the corresponding button, and manualy, i try the 2 solutions ) and i save the changes.
Projeqtor seems calculate if it must generates meeting, but it does'nt generate the new meetings after 30/09/2024, in addition the field "numbers of meetings" is sometimes empty or not updated.
I try severals things, like changing the project end date, nevertheless nothing works....
Which version of ProjeQTOr are you using ?
Hi babynus,
For the moment V11.2.2, i hope update to the lastest quickly...
I didn"t see any info about this point on the release note between 11.2.2 and 11.4.1.
Thank's babynus.
1) 3 patches have been deployed on V11.2 since 11.2.2 (last is V11.2.5)
2) Many fixes have been included on V11.3 and V11.4
3) We only support last stable release on this free support
So be sure to use the latest stable or consider subscribing to professional support to get help on older version.
Thanks
Ok I understand.
Thank you Babynus
Hi babynus,
i'am just update to 11.4.2 and i meet the same issue..
i shew in log there was no error during update. and i check for consistency, it seems OK.
Can you show screenshot of your Periodic Meeting ?