Hello everyone,

Hope someone could help me on this tricky question.

On user documentation i can read "Date de début calculée, en tenant compte de toutes les contraintes. En lecture seule." about the planned start date, same about end date and duration.

First thing :

I think "prévu" is for "planifié" on documentation ? :silly:

Second thing :

Could you explain how those date are calculated ? Specially the first one (start date). And which constraints are you looking for ? 🙂

Thanks in advance.

Regards,


 
Posté : 20/07/2015 8:08 pm
(@babynus)
Posts: 14952
Membre Admin
 

The planned dates are calcilated.... When you run planning calculation.
Use dedicated button on planning screen to see what it does.
Then constdai ts takien into account are detailed on use. Manual and are logic :
Work assigned
Resource availability
Priorities
Predecessors
...


 
Posté : 20/07/2015 8:33 pm
(@nibulus)
Posts: 14
Eminent Member
Début du sujet
 

Could you tell me where is this button please ?

I can't see it.

Thx


 
Posté : 21/07/2015 4:07 pm
(@nibulus)
Posts: 14
Eminent Member
Début du sujet
 

Found !!

Thx


 
Posté : 21/07/2015 4:08 pm