Hello all,

Is there a possibility to filter at the menu activities for activities where the planned end date is later than the validated end date?

Or is it possible to get an alert message when an activity gets over the last milestone (project end). So the planned end date is later than the last milestone? Or is there a report where I can see, that the project/activity will take longer than it should? Similar as the dashboard but just for the critical Projects.

Thanks an best regards


 
Posted : 07 Sep 2017 15H39
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Is there a possibility to filter at the menu activities for activities where the planned end date is later than the validated end date?

No, but on gantt planning view these tasks will appear in red.

Or is it possible to get an alert message when an activity gets over the last milestone

No, not over the last milstone, but an alert is possible when planned end date is over validated end date

Or is there a report where I can see, that the project/activity will take longer than it should?

Tasks are red in gantt chart


 
Posted : 09 Sep 2017 1H10