Planning project with fix time estimate and end date

5 Posts
2 Utilisateurs
0 Reactions
1,323 Vu
Mocni Max
(@mocnimax)
Posts: 45
Active Member
Début du sujet
 
[#8659]

Hi.

I am struggling with correct definition of our project I am importing to ProjeQtOr.
If they are not a bug solving projects, all our projects are defined in similar way - all have fixed effort estimate and fixed end date.
Assigned resources always have more than one overlapping projects active with not defined start dates but end dates.

Up to now I was not able to define project in correct way so they are planned with preserving both fixed values, the effort estimate  and the end date. What ever I do, change or select, at least one of those values is changed. In most of the cases, when I change project parameter, its recalculation change planned effort estimate from defined one to much higher one covering whole period from start date to planned end date.

I know I am doing something wrong, our project definitions are nothing new and strange but am unable to find what is that 🙁 .
Any suggestion and tip is very welcome.
 


 
Posté : 14 Déc AM 00:1212
(@babynus)
Posts: 14952
Membre Admin
 

You must play with planning modes...
Have a look at user manual for more explanation, or consider some training session.


 
Posté : 15 Déc PM 18:1212
Mocni Max
(@mocnimax)
Posts: 45
Active Member
Début du sujet
 

Yes, I would gladly attend a training session and I am waiting for some of them in English.


 
Posté : 15 Déc PM 23:1212
(@babynus)
Posts: 14952
Membre Admin
 

We'll plan sessions in english on Q1 2023.
Check our website from time to time.


 
Posté : 16 Déc PM 15:1212
Mocni Max
(@mocnimax)
Posts: 45
Active Member
Début du sujet
 

Super, will try not to miss it :).


 
Posté : 16 Déc PM 16:1212