Problem the activities of a project created by an admin are being assigned to all the resources

8 Posts
2 Users
0 Reactions
9,858 Views
 imen
(@imenkolsi)
Posts: 37
Active Member
Topic starter
 
[#1111]

Hello again ,
this is time i think that i found an error (or may be something going really wrong in my data ) in projector'ria .

when i create a project from the admin acount. then i create some activities and assign them to a resource

when i try to impute works to this resource i found that all the resource are getting involved in those activities and that project which i found really bizare

( toutes les ressources sont affectées à ce projet )

I deleted the affectation once again and i tryied again to impute to that resource that supposed to be the only one affected to that project and activity but again all resources are affected to that project

for your information the project has "Traning " as a name !

Well my questions are :
1- if an admin create a project , all the resource are immediatly affected to it ?

2- does you have in your code any control on the data for example project that called tranning, all the resource will be affected to it

3- because it seems like a virus to me , did you manage a control if we exceed an average of projects numbers u get that error ?

Thanks I will appreciate any advice 😉


 
Posted : 18 Apr 2013 21H21
(@babynus)
Posts: 14952
Member Admin
 

1- if an admin create a project , all the resource are immediatly affected to it ?

No 😉

2- does you have in your code any control on the data for example project that called tranning, all the resource will be affected to it

No, neither 😛

3- because it seems like a virus to me , did you manage a control if we exceed an average of projects numbers u get that error ?

No, again no...

But I think I know what you're facing... 👿


 
Posted : 19 Apr 2013 3H08
 imen
(@imenkolsi)
Posts: 37
Active Member
Topic starter
 

Can you help me ? tell me what's wrong ?


 
Posted : 19 Apr 2013 10H42
 imen
(@imenkolsi)
Posts: 37
Active Member
Topic starter
 

Please will you help me :'(


 
Posted : 19 Apr 2013 12H03
(@babynus)
Posts: 14952
Member Admin
 

I guess the issue is about the type of your project.
If you set type as "Administrative" (or any other project type with code "ADM"), all the resources have to possibility to enter real work on any of its tasks without needing to be affected to the project, nor assigned to the activities.
These kind of projects are dedicated to "Administrative" projects, for instance to follow-up vacancies, sickness days, training periods, and so on.


 
Posted : 19 Apr 2013 12H28
 imen
(@imenkolsi)
Posts: 37
Active Member
Topic starter
 

Yeah that excatly what i'm facing thanks very much for your help 😉


 
Posted : 19 Apr 2013 12H33
(@babynus)
Posts: 14952
Member Admin
 

You're welcome !!!

and sorry about the little joke managing some suspens :blush:
I wrote this post a bit late in the night 😉


 
Posted : 19 Apr 2013 12H43
 imen
(@imenkolsi)
Posts: 37
Active Member
Topic starter
 

Yes but any way thank you very much for your help 😉


 
Posted : 19 Apr 2013 12H57