Hello,

I have projects, a ticket, activities, an action (and even a Milestone) created in Projeqtor. When I go to the "Planning by resource" feature, I do not know how to see the schedule for a single resource, precision: all the resources are in administrator profile, when I choose from the drop-down menu another resource that the resource "Responsible IT ", I get an error message" No data to display ", while for example for me as a Resource, I have projects assigned to me, and in what is displayed only for the resource" IT Manager ", the tasks assigned to me are visible. I tried to connect with my resource and the operation is the same. I would like to know if it's normal? And what manipulation (s) do I need to perform to view the resource schedule for each resource?

I thank you in advance.

Yours truly.


 
Posté : 22 Mar PM 12:033
(@babynus)
Posts: 14952
Membre Admin
 

Hi

1) Only plannable items can be displayed on planning view, so projects, activities and milestones will be visible, not actions and tickets.

2) to see activities in Resource planning, resource must be assigned to the activity, and planning calculated.

3) if the resource (and not the project leader) goes to planning view or resource planning view, he won't see anything ih he does not have at least read right to the activities


 
Posté : 22 Mar PM 18:033
Cassano Gabriele
(@gabriele)
Posts: 17
Active Member
Début du sujet
 

Good morning,

It's the case, it's for what I don't understand what that does not work ? must I configure other thing(s) ?


 
Posté : 23 Mar AM 11:033
(@babynus)
Posts: 14952
Membre Admin
 

Hi,

Naming the responsible does not "assign" it.
You must you the assignment table


 
Posté : 23 Mar PM 12:033
Cassano Gabriele
(@gabriele)
Posts: 17
Active Member
Début du sujet
 

Sorry but I don't understand what I must do, Could you show me how to do with prinstscreen, I'm a novice on Projeqtor.

Thank you.

Yours.

Gabriele Cassano.


 
Posté : 23 Mar PM 12:033
Paul Ghobril
(@envergus)
Posts: 46
Active Member
 

fill in the assignment as in the figure. I had the same problem at the beginning.


 
Posté : 23 Mar PM 13:033
Cassano Gabriele
(@gabriele)
Posts: 17
Active Member
Début du sujet
 

Thank Envergus, now it work!