Hi,

I run a complex project with many tasks and where many different stakeholders are involved with minimal FTE each.
The second complexity is related to individual timesheet tracking.
Despites many different trials and setups, I cannot figure out how I could properly track progress of each tasks.
Any hints or best practice for Projeqtor ?

Many thanks in advance.

Edgar


 
Posté : 18/04/2019 4:28 pm
(@babynus)
Posts: 14952
Membre Admin
 

Thack progress is done throuch work management.
You define work assigned for each resource, then each resource rgularly enter real work done : you have progress automatically (magic)


 
Posté : 19/04/2019 5:17 pm