Hi again i was wondering about the manner that u calculate the progress (%) in a project
can u pass through the formula
Progress is work driven :
=> Progress = [real work] / [planned work] * 100
=> Progress = [real work] / ([real work] +
) * 100
Since V3.1, there is a new progress, wich is expected progress :
=> Expected = [real work] / [validated work] * 100