Hi,
Why is it that when i closed all activiies for a project, the project status change automaticly to completed
why is tt that when i clode an activity for a project, the project status change for cancelled.
is the a place where i can change this behavior ?
Regards
In global parameters, Planning tab, set to not paramrter to change parent status.
Hi, there is no Planning tab in global Parameters,
is it in the activity tab, Section Automation, settings named "Auto Set parent activity status" ?
Yes it is Activity.
You found the good parameter.