Dear all,
I have created, as suggested, a Administrative project to manage holidays & day off of the team.
Now, i would lile to know where and how I could know if the real working time of one of the resources is over the official working time.
I explain me : for example, A. has thee days off (holidays) and A. spent 100 hours working. So, in real time, I could fin that A. has "114 hours" for july.
But, A. has to work 154 hours.
Where and how I could see that for A., the real working time is 40 hours less than the official working time?
If A. work a lot in August, because he could end some project, and works 200 hours (it's just an example)... Where and how i could see that at the end of August, A. has 154 x 2 - (114 + 200) = 6 hours in overtime.
Etc.
All the best,
Christophe
You can have a look at repords (in Work and Planning section), but I'm not sure any will fit your need.
I tried several times to find in the different reports how to knw how many time one ressource has yet to do or if this ressource has over-worked... but I failed.
I think such a report could be very useful.
All the best
Christophe Noisette
Many planning reports will give that information.
Over work is not planned in ProjeQtOr.
Maybe you could describe what you expect exactly.