Hi
I am trying to check if I can follow my project cost with this wonderful tool.
I set a cost to my resource.
Now I would like to give him an higher salary 😀
So let say the first cost is 100 euro per day, and from 2011/11/01 the cost will be 150.
I wonder if I can do that. There is a "start date" in the "resource cost" form, but the role of this entry is not clear to me.
Moreover, this entry is disabled.
Is this possible to change the cost of a resource from a given date, and if so, how may I do it ?
Best regards
Sky
Hi,
Start date is exactly what you are looking for.
For first cost it is disabed.
For others, it is mandatory.
All is explained in the user Manuel (just hit [F1] key :cool:)
BR
Hi
Thanks. I had check in http://127.0.0.1/projectorria/manual/manual.php before asking but was unable to find the answer.
(I use projectorria V1.7.2). Is it in the activity section ?
(F1 goes to http://support.mozilla.com/fr/home?as=u on firefox 😉 )
Best regards
Sky
Hi
Lastest documentation found at http://projectorria.toolware.fr/manual/manual.php
Clearly more detailed than mine.
Forget my request, it is obsolete.
Best regards
Sky
I confirm : it was not included in V1.7
Manual has been largely completed (and finished) in V1.8.
So you can refer to online manual to get the latest version.