Hi guys
I need to have shared resources like cars, meeting/conferensce rooms, projectors and other stuff. How to declare some resources and assign to them free/busy time, costs, who is using...
Many thank
Alex
Hello,
Non-human resources remain "resources" in their own right and behave and plan themselves in the same way as for a human resource with all the intricacies of existing planning.