Resssources Cost
 
Notifications
Clear all

Resssources Cost

2 Posts
2 Users
0 Reactions
3,361 Views
(@f-arnaudpahntos-com)
Posts: 13
Active Member
Topic starter
 
[#4744]

Hi,

I try to change the day cost of one colleag in my team (Good news for him, I try to increase :cheer: ), but unfortunatly, I receive the following message.

Anybody have an idea ?

Regards


 
Posted : 31 Oct 2017 17H25
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

You face a "Timeout".
Duration of operation is too long for your PHP configuration.

Take care that is you change existing cost, it will be updated for all existing work.
If new cost has effect from given date, create new cost for resource.


 
Posted : 31 Oct 2017 17H28