Hello,
This software will attempt to respect the validated end date, but if a constraint exists elsewhere (generally the availability of resources that is insufficient) so it plans at the earliest but after the validated date because it indicates clearly the reality of things.
It means that is your job as Project Leader to find a solution to get what you want by modifying or cancelling constraints...
Posté : 03/06/2019 4:08 pm