Hello,
I created a project template with somes activities, milsestone.
Some activities have successor and predecessor, and linked element (other activities and/or milestone)
When I copy the template to create a new project, I choose to copy only project structure.
In my new project, I have correctly activities, milsestone, predecessor and successor but I don't have the linked elements 🙁
Is it the right operating mode ? Is there a way to keep the linked element (if it is activitie or milestone) ?
If not, is it possible as "new feature" in a future release ? 🙂
Regards,
Damien
-----------------------------------------------
.
ProjeQtOr v12.1.0 - Apache v2.4.56 - MariaDB v10.4.28 - PHP v8.2.4
Plugins installed : PersonalizedTranslation 1.6 - ScreenCustomization 7.2
If not, is it possible as "new feature" in a future release ?
May be in version 5.4.0
See ticket: 1769