[SOLVED] Administrative project activities not showing up in Gantt

4 Posts
2 Users
0 Reactions
3,227 Views
(@papjul)
Posts: 143
Active Member
Topic starter
 
[#2682]

Hi,

We would like to foresee if too many resources are taking their Christmas holidays at the same time so we created an administrative with a "days off" activity (as you suggested in another topic) and everyone input their holidays on Real Work Allocation.

Unfortunately, when we select the project Administrative on top left of the application, and we go to Resource planning screen, I have the message "No data to display". Were these activities hidden on purpose? How can I disable that?

Thank you,


 
Posted : 28 Oct 2015 15H38
(@babynus)
Posts: 14952
Member Admin
 

Administrative projects are not displayed in Gant chart.
It is designed this way : administrative project are not "planned"

Resource planning would not halp you for what you expect : you would just see a bar from first day out to last day out, even if resouce is working in between.
Use reports for what you expect.


 
Posted : 28 Oct 2015 17H38
(@papjul)
Posts: 143
Active Member
Topic starter
 

What is the report to use for that case?


 
Posted : 02 Nov 2015 11H48
(@papjul)
Posts: 143
Active Member
Topic starter
 

Okay, I found it (planning -> monthly something, for the record).
Solved, thank you!


 
Posted : 02 Nov 2015 11H54