Copied project with a long list of activities. Is it possible to at least bulk update the status from copied to identified? It appears that the overall, the ability to do bulk updates to long rows of data with ProjeQtOr is limited. I can understand from a design consideration how that could be, but, it makes working with large projects and making multiple changes to tasks, activities, milestones VERY tedious. Am I missing something in the functionality? I've searched the forums and the manual for batch, bulk update, bulk edits, etc. and found little.


 
Posté : 19/12/2020 10:45 pm
(@ma_bou)
Posts: 24
Trusted Member
 

Hello,
You can do multiple update on activities by going on the activity screen and selecting the appropriate button in the menu of the details windows. Make sure your project is selected in the top bar for easier operation.

The same principle applies for ticket, milestone etc.

Hope that helps.


 
Posté : 21/12/2020 3:52 pm
(@projectcompliance)
Posts: 6
Active Member
Début du sujet
 

Thank you! I would've NEVER found that functionality, and boy did I look.


 